With the construction office set to be demolished, the Supervisory crew moved their office into the future student library. Today we had a meeting with the contractors about the plans for delivery of the completed building on April 30. It felt wonderful to already be using the offices. And it is exciting to be almost done - the contract called for a May 22 completion date so the contractors will have completed the job more than 3 weeks early. Considering we slowed down the work due to COVID-19 prevention measures, this is an impressive achievement.